Category Archives: Uncategorized

  • -

A Case Study –Blast Damaged Industrial Building – Insurance claim settlement

Category : Uncategorized

Managing Director – Construction Diagnostic Centre Pvt. Ltd., India
E-mail – ranaderavi@gmail.com

Abstract : –

In one of the chemical manufacturing Industry in Maharashtra, the chemical vessel exploded damaging the RCC structure of the building. Insurance company wanted to assess the extent of damage caused by this blast. Hence a detail investigation was carried out by CDCPL. The owner company had claimed for a total damage of the building; but the investigation revealed only a localised damage.

Blast Damage Assessment Audit : –

This case study reveals the facts about blast damage assessment. The assessment work involved Structural Condition Survey (Structural Audit), collection of data / information from site and from client, conducting various Non-destructive tests, and finding out the extent of damage in RCC building

The detail activities carried out under all above scope of work were as below –
Structural Condition Survey (Structural Audit)

  • Detail inspection of the entire structure
  • Photographic survey
  • Noting various observations such as load transfer system, Structural framing system, Structural deficiencies, settlement if any, Cracks in RCC members, Cracks in masonry / plaster, Leakages, Loads on structure, corrosion, defects in non structural elements etc.
  • Identification of broad areas / locations in the structure requiring further detail investigation and for conducting various ND Tests

Conducting various Non Destructive Tests

  • Ultrasonic Pulse Velocity test – Direct& Semi- direct Methods
  • Rebound Hammer Test
  • Core Test
  • Carbonation Test
  • Half-Cell Potential Test
  • Chloride & Sulphate Content test
Details of Structures : –
No. of floor Partly Ground + upper two floors,
Partly Ground + upper Six floors
Partly Ground + upper seven floors
Year of construction Old plant – 1989 & New plant – 2006
Type of construction RCC & Steel frame structure
Walls – Superstructure BBM – 230 mm. thk
Roofing RCC slab & MS rafter with A.C. sheets
Use of Structure Industrial – Chemical Manufacturing

History of past Repairs / Modifications

  • The structure was constructed in two stages. The first building was constructed in 1989 and an extension to this building on west side was done in in 2006.
  • Some of the RCC members ( Columns ) were strengthened ( Jacketed ) in 2011-12.
  • In the past, some changes in machinery / vessels were carried out, but no data / record was available to know whether the structural members were checked for its capacity for this new / additional loads
Data / Information Changes Remarks
Details / Records of any repairs , modifications No —-,
Roof waterproofing No Original waterproofing, cracked at many places, needs replacement
Architectural / plan changes Partly Horizontal & vertical extension of building. Construction of steel towers and shed over RCC terrace
Structural changes Partly Horizontal & vertical extension of building was carried out, but no information available, whether the lower RCC structure was designed / checked to take load of upper steel tower structures
Structural / Corrosion repairs / strengthening Yes Some of the RCC members ( Columns ) were strengthened ( Jacketed ) in 2011-12, as vertical cracks were noticed in these columns. But probably no anti-corrosive treatment was given to these members, reinforcement. The columns are jacketed with micro-concrete of about 25 to 75 mm thickness. In some of the jacketed portion of columns additional bars were provided, but some of the columns were jacketed without any new bars. The additional bars are not extended in bottom and top slab, beams
Changes in Machinery Layout Yes But details / records of old and new machinery layout and loads not available

Observations

  • One of the vessel resting on first floor beams was blasted. The roof slab over the blasted vessel was totally damaged, the adjoining slab near staircase was also totally damaged.
  • Other than this slab no other RCC members at other locations and on other lower floors were having any visible crack / deflection caused due to the said blast.
  • Due this blast, the plaster over some RCC slabs, beams, columns and walls had de-bonded. The RCC jali around the blast area was damaged at almost places.
  • Majority of the RCC members were noticed to have moderate to severe corrosion cracks and spalling of cover concrete.
  • Foundations could not be inspected, but the superstructure was not having any visible signs indicating possibility of the settlement of foundations.
  • The other observations are as reported below.
Overall Observation Severity Location, Cause & Effect
Signs of foundation settlement Nil —-
Structural Cracks in RCC members Severe Roof beam (+11 m Lvl) around vessel blast area
Corrosion Cracks in RCC members Moderate to Severe Majority of the RCC members
Corrosion of structural steel members Rusting / Scaling / Pitting Moderate to severe Some columns& Beams were having severe corrosion, with threat to safety of the structure, requiring an immediate intervention. While some other columns and beams were having minor to moderate corrosion
Spalling of cover concrete Moderate to Severe Majority of the RCC members were having moderate to severe corrosion cracks and spalling of cover concrete mainly due to corrosion.
Cracks in walls / Plaster Minor to Severe At some places ( new building ) ceiling plaster and at some places the plaster and cover concrete of beams and columnhad fallen due to blast impact. Probably this plaster / cover concrete had already cracked and de-bonded due to severe corrosion of reinforcement.
Deflections / Sag / Tilt in RCC / Steel members Severe Roof Slab (+11 m Lvl) near stair around vessel blast area had a huge deflection
Deflections / Sag / Tilt in Walls Nil —-
Honeycombing in RCC members Nil —-
Crushing , crumbling of concrete Roof Slab over blasted vessel & near stair (+11 m Lvl) was totally
Leakages from roof slab / Roofing sheets Moderate Roof slab
Leakages from Toilet slabs —-
Leakages in Walls Nil —-
Abnormal loading / Overloading –
Constructional defects Minor to Moderate Steel column of 4th floor, of east side tower buckled at joint.Some of the steel columns are placed eccentrically above lower level columns.
Structural Deficiencies Nil —-
Condition of drainage / water lines, Gutters —- —-
Vegetation over walls , RCC members, Plumbing pipes Nil  
Ground / Parking floor / Drainage chamber settlement
OH Tank / Ground Tank – Leakages from roof slab , bottom slab, tank walls —-
Structure / Members exposed to Aggressive Exposure Condition Severe The entire building is exposed severe corrosive fumes
Suspended loads – Stability of False Ceiling, Heavy hanging fixtures Nil —-
Roof sheets / Cladding sheets cracked / damaged Minor  
Other – —- —-
Front view of the buildings
Ground floor Apparently no structural cracks in any of members due to blast
Ground floor Apparently no structural cracks in any of members due to blast
RCC / Steel members around blasted area
RCC / Steel members around blasted area
Totally damaged roof slab due to Blast ( Two slab panels
Totally damaged roof slab due to Blast ( Two slab panels
case-study-slider8
Totally damaged roof slab due to Blast
Roof slab adjacent to staircase – crackd and lifted up
Roof slab adjacent to staircase – crackd and lifted up
Roof slab adjacent to staircase – crackd and lifted up
Roof slab adjacent to staircase – crackd and lifted up
Roof slab adjacent to staircase – crackd and lifted up
Moderate to Severe corrosion of reeinforcement along with spalling of cover concrete
Moderate to Severe corrosion of reeinforcement along with spalling of cover concrete
Ceiling plaster fallen due to blast
Ceiling plaster fallen due to blast
Plaster over RCC member fallen and parapet wall & RCC Grill collapsed due to blast
Plaster over RCC member fallen and parapet wall & RCC Grill collapsed due to blast
All columns of old building were jacketed with Micro-Concrete 25 to 75 mm thick
All columns of old building were jacketed with Micro-Concrete 25 to 75 mm thick
All columns of old building were jacketed with Micro-Concrete 25 to 75 mm thick
All columns of old building were jacketed with Micro-Concrete 25 to 75 mm thick
Structural steel members with minor to moderate corrosion
Structural steel members with minor to moderate corrosion
Structural steel members with minor to moderate corrosion
Structural steel members with minor to moderate corrosion
Structural steel members with minor to moderate corrosion
Structural steel members with minor to moderate corrosion
Structural steel members with Severe corrosion
Structural steel members with minor to moderate corrosion
Structural steel members with minor to moderate corrosion
Structural steel members with Severe corrosion
Bend at column joint
Bend at column joint
Misaligned Structural Column of staircase of east side Steel tower
Front view of the buildings Ground floor Apparently no structural cracks in any of members due to blast Ground floor Apparently no structural cracks in any of members due to blast RCC / Steel members around blasted area RCC / Steel members around blasted area Totally damaged roof slab due to Blast ( Two slab panels Totally damaged roof slab due to Blast ( Two slab panels case-study-slider8 Totally damaged roof slab due to Blast Roof slab adjacent to staircase – crackd and lifted up Roof slab adjacent to staircase – crackd and lifted up Roof slab adjacent to staircase – crackd and lifted up Roof slab adjacent to staircase – crackd and lifted up Roof slab adjacent to staircase – crackd and lifted up Moderate to Severe corrosion of reeinforcement along with spalling of cover concrete Moderate to Severe corrosion of reeinforcement along with spalling of cover concrete Ceiling plaster fallen due to blast Ceiling plaster fallen due to blast Plaster over RCC member fallen and parapet wall & RCC Grill collapsed due to blast Plaster over RCC member fallen and parapet wall & RCC Grill collapsed due to blast All columns of old building were jacketed with Micro-Concrete 25 to 75 mm thick All columns of old building were jacketed with Micro-Concrete 25 to 75 mm thick All columns of old building were jacketed with Micro-Concrete 25 to 75 mm thick All columns of old building were jacketed with Micro-Concrete 25 to 75 mm thick Structural steel members with minor to moderate corrosion Structural steel members with minor to moderate corrosion Structural steel members with minor to moderate corrosion Structural steel members with minor to moderate corrosion Structural steel members with minor to moderate corrosion Structural steel members with minor to moderate corrosion Structural steel members with Severe corrosion Structural steel members with minor to moderate corrosion Structural steel members with minor to moderate corrosion Structural steel members with Severe corrosion Bend at column joint Bend at column joint Misaligned Structural Column of staircase of east side Steel tower

Non Destructive Testing observations

  • The original grade of concrete of both the wings ( old and new ) was not known. Considering the year of construction, probably the grade of concrete of old building could be M-15 and that of new building being constructed in 2006, should be M-20. But as there was no data available to confirm this, we had assumed the grade of concrete of both the wings as M-15
  • The core test results indicated a very wide range in strength of concrete for both the wings as below –
    • Old building – M – 09 to M – 32
    • New building – M – 08 to M – 38
    • New building ( blasted area Grid A2-A3-B2-B3) – M – 14 to M – 30
  • The Rebound Hammer & Ultra Sonic Pulse velocity test results also indicated a very wide range in strength of concrete for both the wings as below –
    • Old building – M – 17 to M – 32
    • New building – M – 06 to M – 26
    • New building ( blasted area Grid A2-A3-B2-B3) – M – 06 to M – 27

The strength of site concrete was predicted by carrying out a regression analysis on combined NDT methods – Rebound Hammer Test, UPV Test and Core test.

The qualitative assessment of concrete quality was done based on below table –

At CDC we have carried out extensive research on quality assessment and it has been observed that, the quality gradation as per IS – 13311 (part-1)- 1992 is valid ONLY for M – 15 grade concrete and only for direct probing method. For concrete with more than M – 20, we recommend to grade the quality of concrete as per below given table –

Gradation of Quality of concrete ( as per CDC )
Direct & Semi-Direct velocity Km/Sec.
Quality of Concrete < 15 Mpa 20 to 25Mpa 30 to 35Mpa > 40Mpa
Excellent More than 4.000 More than 4.400 More than 4.600 More than 4.900
Good 3.500 to 4.000 3.750 to 4.400 3.900 to 4.600 4.150 to 4.900
Medium 3.000 to 3.500 3.400 to 3.750 3.600 to 3.900 3.800 to 4.150
Doubtful Less than 3.000 Less than 3.400 Less than 3.600 Less than 3.800
Gradation of Quality of concrete ( as per CDC )
Indirect velocity Km/Sec.
Quality of Concrete < 15 Mpa 20 to 25Mpa 30 to 35Mpa > 40Mpa
Excellent More than 3.500 More than 3.900 More than 4.100 More than 4.400
Good 3.000 to 3.500 3.250 to 3.900 3.400 to 4.100 3.650 to 4.400
Medium 2.500 to 3.000 2.900 to 3.250 3.100 to 3.400 3.300 to 3.650
Doubtful Less than 2.500 Less than 2.900 Less than 3.100 Less than 3.300
Members Total Testing members Total Testing Location % Velocity below 2.5 km/Sec. % Velocity 2.50 to 3.00 Km/Sec. % Velocity 3.00 to 3.50 Km/Sec. % Velocity 3.50 to 4.00 Km/Sec. % Velocity Above 4.00 Km/ Sec.
New Building (Blasted Area)
Columns 12 24 12.50% 45.83% 33.33% 8.33% 0.00%
Beams 13 26 26.92% 46.15% 19.23% 7.69% 0.00%
New Building
Columns 36 72 25.00% 27.77% 40.27% 6.94% 0.00%
Beams 76 130 35.07% 20.89% 29.85% 12.68% 1.49%
Slabs 18 44 11.36% 22.72% 40.90% 25.00% 0.00%
Old Building
Beams 31 62 17.74% 35.48% 33.87% 9.67% 3.22%
Slabs 12 34 0.00% 26.74% 44.11% 29.41% 0.00%
New Building (Slab Near Blasted Area)
Slabs 6 12 16.66% 25.00% 25.00% 33.33% 0.00%

The Half-Cell Potential test indicated that at majority of the test locations, there was a more than 90 % possibility of corrosion

% Half cell Potential < -200 ( mV ) % Half cell Potential < -200 to -350 ( mV ) % Half cell Potential < -350 to -500(mV) % Half cell Potential > -500 (mV)
Combined Report
New Building
Columns 6.48% 50.00% 27.05% 16.5%
Beams 8.80% 37.60% 46.40% 7.2%
Slabs 9.10% 50.00% 30.30% 10.6%
Tie Beams 0.00% 0.00% 20.00% 80.0%
Old Building
Beams 0.00% 40.00% 40.25% 19.0%
Slabs 0.00% 75.00% 0.00% 25.0%
Tie Beams 0.00% 0.00% 70.00% 30.0%

Interpretation of Hal-Cell Potential test results

  • If potentials over an area are numerically less than – 200 mV Copper – Copper sulphate half cell, there is a greater than 90 % possibility that, no reinforcing steel corrosion is occurring in that area at the time of measurement.
  • If potentials over an area are in the range of – 200 mV to – 350 mV Copper – Copper sulphate half cell, then the corrosion activity of reinforcing steel in that area is uncertain.
  • If potentials over an area are numerically greater than – 350 mV Copper – Copper sulphate half cell, there is a greater than 90 % possibility that, reinforcing steel corrosion is occurring in that area at the time of measurement.

Hello world!

Category : Uncategorized

Welcome to WordPress. This is your first post. Edit or delete it, then start writing!